3.1 · Agricultural and functional zoning
Organise suitable native-tree windbreaks, including ghaf, sidr and arak, alongside crops, vegetables, palms, intercropping and bee forage. Allocate recycling, compost and biological-input zones, and assess rotational grazing and livestock integration against land, water, safety and permissions.
3.2 · Precision irrigation and the water cycle
Design drip and subsurface irrigation where appropriate, linked to soil moisture and weather, with suitable runoff harvesting. The document targets over 40% reduction in water losses, requiring baseline and field validation. Separate wastewater streams and define treatment and reuse by water type, quality and authorised use.
3.3 · Green infrastructure, manufacturing and smart control
The concept includes Industry 5.0-oriented honey processing and robotic sorting/packing, a quality laboratory and batch traceability, training centre, separate lodge, worker housing, stores and an AI Hub. These connect to a recycling station designed and operated to deliver green circular-economy objectives, ASP composting, water treatment, sensors, weather stations, drones and rooftop/canopy solar with load and storage studies.
3.4 · Land allocation and building footprint
The detailed schedule proposes 2,118.20 m² of enclosed building footprint, approximately 7.60% of the site. The remaining 25,752.80 m² includes fields, windbreaks, roads and composting; it is not all eligible agricultural carbon area. This planning ratio establishes neither a statutory allowance nor carbon additionality.
3.5 · Climate orientation, circulation and indoor quality
Review sun, wind, setbacks and odour dispersion before fixing treatment locations; the northwest corner is not automatically downwind of northwesterly winds. Target external parking, light electric transport, perimeter loading and safe permeable routes. Separate service areas from soil sampling and specify suitable low-emission materials, insulation, shading, ventilation and filtration.
Proposed facility and area schedule
The schedule below follows the attachment’s detailed table labelled as the latest update. Some sketch figures and earlier descriptions differ; reconcile dimensions, areas and locations in one coordinated plan before execution approval.
Whole site27,871.00 m²
Proposed enclosed footprint2,118.20 m²Approximately 7.60% of site
Remaining allocations25,752.80 m²Agriculture, services and circulation
Enclosed facilities · planning areas in square metres| Facility and area | Proposed location | Concept and function |
|---|
| Vocational and environmental training centre650.00 m² | Southern frontage near the entrance | Learning ring and courtyard, rooms, workshops and laboratory; reconcile diameters and floor areas in detailed design. |
|---|
| Honey facility and quality laboratory300.00 m² | Northeast site perimeter | Eight-cell hexagonal concept, controlled production flow, hygiene zoning and perimeter loading. |
|---|
| Sustainable owner’s lodge300.00 m² | Southeast sector | Organic-leaf concept, privacy, shading, insulation and indoor environmental quality. |
|---|
| Worker housing and sanitary facilities300.00 m² | Western service sector | Adaptable modular arc, separate from the lodge, with safe living spaces and suitable ventilation. |
|---|
| Machinery store and workshop150.00 m² | Western sector | Store, maintain and calibrate minimum/no-till machinery. |
|---|
| AI Hub and dMRV control room138.20 m² | Central connection between learning and fields | Manage sensors, irrigation, data and records; specify insulation and cooling from equipment loads. |
|---|
| Biological-input store100.00 m² | Southwest sector | Appropriate storage conditions, batch traceability, segregation and contamination prevention. |
|---|
| Water treatment and reuse station180.00 m² | Adjacent treatment zone, subject to assessment | Assess MBBR, filtration and disinfection against water characteristics and reuse permissions. |
|---|
| Scheduled footprint total | 2,118.20 m² |
|---|
ASP recycling and composting unit
300.00 m²Proposed treatment area; review construction/environmental classification and monitor CH₄/N₂O, odour and leachate.
Routes and logistics apron
2,100.00 m²Coordinate facility access, walking, emergency routes and perimeter loading; verify swept paths.
Tree windbreaks
3,650.00 m²Perimeter planting with indicative 5–8 m widths; reconcile area and orientation in the plan.
Regenerative fields and bee forage
19,702.80 m²Crop, cover and apiary sectors; establish eligible carbon-accounting area separately.
Solar is proposed on roofs and parking canopies without additional ground allocation in this table, subject to load, available-area, structural and storage studies. Area classification and building allowances require authority confirmation. Estidama assesses buildings; Verra registers carbon projects and issues credits. Neither confers the other.
Explore the full facility directory ↗- Phase deliverables
- Coordinated masterplan, area schedule, CAD/BIM drawings, water and energy balances, specifications, quantities, circulation and permitting plans.
- Review checkpoint
- Reconcile areas, dimensions and disciplines and approve the design; organic forms or solar alone do not establish performance or certification.